E.D. Swett

Since 1936, we’ve led the way in bridge building for the New Hampshire, Massachusetts, and Vermont regions.

Photos from E.D. Swett's post 06/14/2024

June 14, 2024 NHDOT I-93 NB Bridge Rehabilitations Manchester. Lowering crane matts down under the Stevens Pond Bridge in preparation for repairing the existing pier.

06/11/2024

June 11, 2024 Tully Brook Road Bridge Replacement Richmond. Project Superintendent Buzz Abbott, Foreman Curtis LaBrecque, Foreman Jason Bisson, operator Randy Gibson, craftsmen Jon Gibson, Dave Clark and Branden Stellar placed the new abutment A wall today. The backwall placement is set for Friday. Excellent work

Photos from E.D. Swett's post 06/11/2024

June 11, 2024 ADA Transfer Ramp Bridge Nashua. Project Foreman Lon Collins, Yard Foreman Jim Lacasse, operator Jim Conway, craftsmen Derek Boynton, Scot Frechette and Dzevad Tokovic place the concrete landing slab for the ramp. Nice work

06/10/2024

June 10, 2024 ADA Transfer Ramp Bridge Nashua. Project Foreman Lon Collins, operator Jim Conway craftsmen Scot Frechette and Dzevad Tokovic preparing to place the concrete landing slab tomorrow. Excellent work.

Photos from E.D. Swett's post 06/04/2024

June 4, 2024 NHDOT I-93 NB Bridge Rehabilitations. Project Superintendent Mike Desroches, Foreman Craig Moses, operator Mark Bailey, craftsmen Vic Davis, Rick Griffin, Ed Coulstring and Alex Coughlin have removed all existing deck asphalt off of Wellington Road Bridge and 90 % off of Stevens Pond Bridge. Excellent work.

05/31/2024

May 30, 2024 Tully Brook Road Bridge replacement Richmond. Foreman Jason Bisson, Foreman Curtis LaBrecque, operator randy Gibson and craftsmen Bill Libby forming up the abutment A footing. Nice work

Photos from E.D. Swett's post 05/31/2024

May 31, 2024 NHDOT I-93 NB Manchester Project Superintendent Mike Desroches and ED Swett family members removing asphalt off the existing bridge decks on Stevens Pond and over Wellington Road: Phase 1. Excellent work

Photos from E.D. Swett's post 05/29/2024

May 29, 2024 NHDOT I93 NB Manchester. Project Superintendent Mike Desroches, Foreman Craig Moses, operator Mark Bailey, Craftsmen Ed Coulstring and Alex Coughlin starting to pick up steam on the project, no that traffic is switched. Our siub-contractor, Continental Paving, milling the existing asphalt of the bridge decks.

05/29/2024

May 29, 2024 ADA Transfer Ramp Cotton Mill Nashua. Project Foreman Lon Collins, operator Jim Conway and craftsmen Scot Frechette and Dzevad Tokovic forming up the walls on top of the footing for the landing slab. Nice work.

Photos from E.D. Swett's post 05/23/2024

May 22, 2024 Tully Brook Road Bridge Replacement Richmond. Foreman Jason Bisson, operator Randy Gibson and craftsmen Bill Libby and Dave Clark placed 267 CY concrete sub-footing at abutment A. Excellent work by these guys.

Photos from E.D. Swett's post 05/22/2024

May 21, 2024 NHDOT I93 NB Manchester bridge reconstruction work. Project Superintendent Mike Desroches, Foreman Curtis LaBrecque, Foreman Craig Moses and ED Swett family members working thru the nights on Sun 5/19, Mon 5/20, Tue 5/21, wed 5/22 and Thur 5/23 switching traffic into the phase 1 configuration. Excellent work and dedication by all these men.

05/21/2024

May 21, 2024 NHDOT Rte 202 Bridge Replacement over Contoocook River Peterborough. Our sub-contractor, L&D Striping, installing final lane lines throughout the project.

Photos from E.D. Swett's post 05/21/2024

May 21, 2024 City of Manchester Rail Trail: Ribbon cutting ceremony today. Excellent work by Project Foreman Lon Collins and the rest of the ED Swett family memebers.

Photos from E.D. Swett's post 05/16/2024

May 16, 2024 Lebanon Tunnel, Lebanon Project Superintendent Michael Desroches and craftsmen Nate Puluti visited the tunnel today to complete some additional punch list items, so they snapped some pictures of the art work created on the tunnel walls by the Lebanon community. Very nice.

Photos from E.D. Swett's post 05/13/2024

May 13, 2024 Tully Brook Road Bridge Replacement Richmond. Pile Foreman Jason Bisson, operator Randy Gibson and craftsmen Bill Libby excavating inside Abutment A cofferdam in preparations for placing the sub-footing. Nice work.

05/10/2024

May 2024 edition of "New Hampshire Good Roads Association" magazine.

Photos from E.D. Swett's post 05/10/2024

May 10, 2024 ADA Cotton Mill Transfer Bridge Nashua. Project Foreman Lon Collins coordinating our sub-contractor, Rain For Rent, in preparation to dewater the contaminated water in the cofferdam utilizing a frac tank collection system.

Photos from E.D. Swett's post 05/10/2024

May 9, 2024 NHDOT I93 Northbound Bridge Rehabilitation Manchester. Project Superintendent Mike Desroches coordinating our sub-contractor, Continental Paving, in paving the existing rumble strips and diversion widening. The 2024 Phase 1 lane shift on NB begins Sunday night May 12.

Photos from E.D. Swett's post 05/07/2024

May 7, 2024 ADA Cotton Mill Transfer Ramp Nashua. Project Foreman Lon Collins, operator Jim Conway and craftsmen Scot Frechette and Dzevad Tokovic constructing the frame work for the ADA ramp. Excellent work

Photos from E.D. Swett's post 04/29/2024

April 29, 2024 NHDOT I-93 NB Bridge Reconstruction Manchester. Project Superintendent Mike Desroches, Foreman Craig Moses, operator Mark Bailey and craftsmen Rick Griffin completing the diversion roadwork and widening as our sub-contractor, Continental Paving, mills and paves in the existing rumble strips for Phase 1. Preparing the project for lane shifting beginning Sunday night, Nice work by everyone.

04/26/2024

April 25, 2024 Tully Brook Road Bridge replacement Richmond. Existing culvert heading to the scrap yard.!

Photos from E.D. Swett's post 04/24/2024

April 24, 2024 Tully Brook Road Bridge Replacement Richmond. E.D. Swett family members removing the existing culvert.

04/24/2024

April 24, 2024 NHDOT I93 NB Manchester. Project Superintendent Mike Desroches, Foreman Craig Moses and operator Mark Bailey building the widenings at the Westbound Rte 101 on ramp and NB 93 merge.

04/24/2024

April 24, 2024 Tully Brook Road Bridge Replacement Richmond. Foreman Jason Bisson, operator randy Bison, craftsmen Bill Libby, Jon Gibson, Carl Olson and Branden Stellar divert the flow of water from existing Tully Brook to in-between the cofferdam sheets and new Abutment B. Nice work.

Photos from E.D. Swett's post 04/23/2024

April 22, 2024 NHDOT Rte 202 Bridge Replacement over Contoocook River Peterborough . Our sub-contractor, Continental Paving, paving binder on entire project today

Photos from E.D. Swett's post 04/18/2024

April 18, 2024 NHDOT I89 Exit 19 Lebanon Bridge Reconstruction
Project Foreman Joe Symonds, craftsmen Vic Davis, Ed Coulstring and Alex Coughlin along with our sub-contractors, BUR Construction and CWS Fence and Guardrail preparing the project for the final paving.

04/16/2024

April 16, 2024 ADA Cotton Mill Transfer Ramp Nashua. Project Foreman Lon Collins, operator Jim Conway and craftsmen Scot Frechette and Dzevad Tokovic constructing the permanent ramp supports #10, #11 and #12 out of 16.

Photos from E.D. Swett's post 04/16/2024

April 16, 2024 Island Street Bridge Keene. Project Superintendent Buzz Abbott, Foreman Curtis LaBrecque, Craftsmen Derek Boynton, Dave Clark, Nate Puluti, Josh Stanford and Vic Davis forming and placing the approach slab keeper blocks.

Photos from E.D. Swett's post 04/16/2024

April 16, 2024 Tully Brook Road Bridge Replacement Richmond. Foreman Jason Bisson, operator Randy Gibson, craftsmen Jon Gibson, Branden Steller, Carl Olson and Bill Libby backfilling Abutment B.

Want your business to be the top-listed Engineering Company in Concord?
Click here to claim your Sponsored Listing.

Telephone

Address

8 Industrial Park Drive
Concord, NH
03301

Other Construction Companies in Concord (show all)
B&M Weldon B&M Weldon
10 FERRY Street, STE 333 #176
Concord, 03301

Residential excavation, hardscaping, and painting. Contact Brooke to chat about your next project.

Cut To Fit Co. Cut To Fit Co.
16 Judith Drive
Concord, 03301

*Granite Curb *Precast Concrete Curb *Hardscaping *Excavation

Jordan Property Services Jordan Property Services
Concord, 03303

ED Swett Inc ED Swett Inc
8 Industrial Park Drive
Concord, 03301

Established in 1936, E.D. Swett is an employee-owned bridge construction company and general contrac

Amplified Construction Amplified Construction
Concord, 03303

Tile and Stone,Inc Tile and Stone,Inc
9 Via Tranquilla Street
Concord, 03301

Tile and Stone

Phoenix Precast Products Phoenix Precast Products
77 Regional Drive
Concord, 03301

Phoenix Precast Products manufactures all manner of precast concrete products.We have many standard stock items and the capability to produce custom items.

North Branch Construction North Branch Construction
76 Old Turnpike Road
Concord, 03301

North Branch Construction: Commercial and Residential Construction Excellence Since 1958.

Currid Builders Currid Builders
11 South Main Street, Unit 200
Concord, 03301

🏡 🔨 DESIGNED ▪ BUILT ▪ LOVED 🔨 🏡 Kitchen & Bath | Major Renovations | Additions

HHR Enterprises HHR Enterprises
Concord, 03301

Residential and Commericial Remodeling

Associated Builders and Contractors New Hampshire/Vermont Associated Builders and Contractors New Hampshire/Vermont
58 Chenell Drive Ste 11
Concord, 03301

Freedom Fighters (www.abcnhvt.org). Serving the Government Relations, Business Development and Human