Philkonstrak Development Corporation

Philkonstrak Development Corporation (PDC) is a private construction firm registered in the Securiti We also excel in the area of construction management.

Philkonstrak Development Corporation (PDC) is a private construction firm registered in the Securities Exchange Commission (SEC) on August 2006 with SEC Registration No: CS200629243. The professional staff at PDC has over 30 combined years of design, engineering and construction experience. Vision:

PDC envisions being the most developed, progressive and leading construction firm globally with the

Photos from Philkonstrak Development Corporation's post 12/12/2023

Pier Enhancement and Development Project: Port Expansion with Roro Ramp

Activities:
-Chipping of excess piles
-Installation of Formworks for pile cap (4 stations?
-Concrete Pouring of Pile cap ( 4 stations)
-Stripping of forms
-Installation of precast beams (1 transverse, 4 longitudinal)
-Installation of precast slabs
-Squareholing 7th and 8th row

Photos from Philkonstrak Development Corporation's post 12/12/2023

CONSTRUCTION OF PILAR ARC, POBLACION PILAR BOHOL

Activities:
-Fabrication & installation of arc main reinforcements
-Finishing/molding works
-Masonry works

Photos from Philkonstrak Development Corporation's post 12/12/2023

Mactan Rock Pipe Laying

Activities:
-75 ln.m Pavement Cutting
-40.50 cu.m. Pavement Breaking
-90.72 cu.m. Excavation
-40.50 cu.m Hauling and disposal of Demolished Materials
-56.70 cu.m. hauling of wash sand for sand Bedding
-18 length Pipe Jointing 400mm PE100-SDR13.6
-18 length Pipe Laying
-56.70 cu.m. hauling of excavated materials for backfilling
-Backfilling with Compaction
-warning tape laying

Photos from Philkonstrak Development Corporation's post 12/12/2023

Proposed 350mm dia and 100mm dia DI, Transmission and Distribution Pipeline Project

Activities from 12.04 - 12.09.23
• Concrete Breaking - 48.60m
• Excavation - 48.60m
• Pipe Laying 350mm DI Pipe - 9 lengths Total Pipe Laying 350mm DI Pipe
as of 12/9/23 - 38 lengths
• Hauling of Sand & Excavated Materials
• Hauling & Lifting of power tools & barricades
• Backfill & Compaction
• Laying of Warning Tape
• Sand Bedding
• Hauling of DI Pipe to Mactan
• Cutting of Concrete Pavement

Photos from Philkonstrak Development Corporation's post 12/12/2023

Design and Build of Site Development-PSHS CVisC

Activities:
Solar Street Light w/ Lamp Post
-Concrete Pouring of pedestal

Grouted riprap
-Finishing works on concrete stairs
-Application of Lean Concrete

Entrance Symbol
-Weaving of Rattan
-Installation of Stainless Steel Flame Panels

Covered Walk
-Finishing/Plastering works on RC columns
-Installation/Welding of Sag Rods

Road 2 (Admin to Gym)
-Excavation and laying of gravel bedding for curb and gutter
-Concrete works for curb and gutter
-Finishing/Plastering works for curb and gutter
-Rectification of trench drain concrete

Slope Protection
-Installation of Rebars
-Application of Geotextile
-Concrete Pouring

Photos from Philkonstrak Development Corporation's post 11/12/2023

DESIGN AND BUILD OF CARRASCAL WATER SUPPLY SYSTEM IMPROVEMENT PROJECT (PHASE II)

Activities:
- Excavation of Natural Ground for Pipe Trenching of 6" dia. PE Pipe @ Brgy. Gamuton
- Jointing of 6" dia. PE Pipes @ Brgy. Gamuton
- Laying of 6" dia. PE Pipes @ Brgy. Gamuton
- Installation of Detectable Warning Tape for 6" dia. PE Pipes @ Brgy. Gamuton
- Backfilling of Excavated Soil for 6" dia. Pipe Trench @ Brgy. Gamuton
- Hydrotesting of 540ln.m. 8" dia. PE Pipe @ Sta. 1+589.64 to Sta. 2+187.33, Brgy. Gamuton

Photos from Philkonstrak Development Corporation's post 05/12/2023

INFRA 2023-08-022 Road Concreting of Farm to Market Roads, Dumanjug, Cebu

Activities:
- Concrete Pourin6
- Installation of. FORMWORKS
- CLEARING OF AREA
- HAULING OF MATERIALS
- HAULING OF WATER
- CONCRETE POURING OF EXTENSIONS 1 METER
- CUTTING AND ASPAHLTINNG
- SHOULDERING OF ROAD

Photos from Philkonstrak Development Corporation's post 05/12/2023

Proposed 350mm dia and 100mm dia DI, Transmission and Distribution Pipeline Project

Activities:
• Concrete Breaking - 21.60m
• Excavation - 21.60m
• Pipe Laying 350mm DI Pipe - 4 lengths Total Pipe Laying 350mm DI Pipe
as of 12/2/23 - 29 lengths
• Hauling of Sand & Excavated Materials
• Hauling & Lifting of power tools & barricades
• Backfill & Compaction
• Laying of Warning Tape
• Sand Bedding
• Hauling of DI Pipe to Mactan
• Cutting of Concrete Pavement

Photos from Philkonstrak Development Corporation's post 05/12/2023

Design and Build ofSite Development-PSHS CVisC

Activities:

Road 1
-Fabrication of Manhole

Grouted Riprap
-Excavation for stairs facing school canteen
-Installation of formworks for stairs facing school canteen
-Concrete Pouring for stairs facing school canteen
-Stripping of formworks and plastering/finishing works of stairs
-Laying of riverstones and stone masonry works for walls adjacent to stairs
-Application of lean concrete

Covered Walk
-Metal and welding works for roof frame (2"x3" beam, 2"x4"girder, c-purlins)

Road 2 (Admin to Gym)
-Excavation and laying of gravel bedding for curb and gutter
-Concrete pouring for curb and gutter
-Finishing/Plastering works for curb and gutter

Road 2 (Annex to Admin)
-Excavation and laying of gravel bedding for road drainage
-Installation of rebars for road drainage
-Concrete Pouring for road drainage

Road Safety and Directional Signages
-Preparation of road signages

Slope Protection
-Installation of Rebars
-Installation of Formworks
-Concrete Pouring

Solar Street Lighting
-Excavation for street light pedestals
-Installation of rebars and formworks for pedestals

Entrance Symbol
-Welding works and cleaning of flame panels
-Weaving of rattan

Photos from Philkonstrak Development Corporation's post 04/12/2023

Mactan Rock Pipe Laying

Activities:
-Pavement Cutting
-Pavement Breaking
-Excavation
-Hauling of Excavation Materials
-Hauling of wash sand for sand Bedding
-Sand Bedding
-Pipe Jointing 400mm PE100-SDR13.6
-Pipe Laying
-Hauling of excavated materials for backfilling
-Backfilling with Compaction
-Hauling and disposal of surplus excavated materials
-Warning tape laying

Photos from Philkonstrak Development Corporation's post 04/12/2023

PROPOSED MOALBOAL BULK WATER SUPPLY (PHASE II)

ACTIVITIES FROM NOV. 25- DEC 1
-Pipelaying of 6” pipe . Basdiot: 37 lengths
-Pavement breaking . Basdiot
-Clearing of excavated areas . Basdiot & Tuble
-Pipelaying 6” pipe . tuble: 19 lengths
-Excavation works . Tuble :474.76 ln.m
-Sand bedding . Basdiot &Tuble
-Laying of Warning tapes
-Backfilling works
-Clearing of Driveways

Photos from Philkonstrak Development Corporation's post 04/12/2023

DESIGN AND BUILD OF CARRASCAL WATER SUPPLY SYSTEM IMPROVEMENT PROJECT (PHASE II)

Activities:
- Excavation of Natural Ground for Pipe Trenching of 8" dia. PE Pipe @ Brgy. Gamuton
- Jointing of 8" dia. PE Pipes @ Brgy. Gamuton
- Laying of 8" dia. PE Pipes @ Brgy. Gamuton
- Installation of Detectable Warning Tape for 8" dia. PE Pipes @ Brgy. Gamuton
- Backfilling of Excavated Soil for 8" dia. Pipe Trench @ Brgy. Gamuton
- Excavation of Natural Ground for Pipe Trenching of 6" dia. PE Pipe @ Brgy. Gamuton
- Jointing of 6" dia. PE Pipes @ Brgy. Gamuton
- Laying of 6" dia. PE Pipes @ Brgy. Gamuton
- Installation of Detectable Warning Tape for 6" dia. PE Pipe @ Brgy. Gamuton
- Backfilling of Excavated Soil for 6" dia. Pipe Trench @ Brgy. Gamuton
- Continuation of Demolition of Existing Road Accessways that can obstruct in Laying of 6" dia. PE Pipes @ Brgy. Gamuton
- Installation of 10" dia. Sleeve Coupling Fitting @ Sta. 1+256.98, Brgy. Panikian, Carrascal
- Thrust Blocking of 10" dia. Sleeve Coupling @ Sta. 1+256.98, Brgy. Panikian, Carrascal

Photos from Philkonstrak Development Corporation's post 29/11/2023

Proposed 350mm dia and 100mm dia DI, Transmission and Distribution Pipeline Project

Activities:
• Concrete Breaking - 48m
• Excavation - 43.20 sq.m
• Pipe Laying 350mm DI Pipe - 8 lengths Total Pipe Laying 350mm DI Pipe
as of 11/25/23 - 25 lengths
• Hauling of Sand & Excavated Materials
• Hauling & Lifting of power tools & barricades
• Backfill & Compaction
• Laying of Warning Tape
• Sand Bedding
• Hauling of DI Pipe to Mactan
• Cutting of Concrete Pavement

Photos from Philkonstrak Development Corporation's post 29/11/2023

Mactan Rock Pipe Laying

Activities:
-Pavement Cutting
-Pavement Breaking
-Excavation
-Hauling of Excavation Materials
-Sand Bedding
-Pipe Jointing 400mm PE100-SDR13.6
-Pipe Laying
-Backfilling with Compaction
-Hauling and disposal of surplus excavated materials

Photos from Philkonstrak Development Corporation's post 29/11/2023

MOALBOAL BULK WATER SYSTEM PHASE 2

Activities:
- HARD EXCAVATION (320 ln.m)
- PIPE LAYING (51 lengths 160mm HDPE)
- SANDBEDING
- BACKFILLING (306 ln.m)
- PLACING OF WARNING TAPE
- REPAIR OF DAMAGE UTILITIES
- MANUAL EXCAVATION
- BUTTFUSION

Photos from Philkonstrak Development Corporation's post 28/11/2023

DESIGN AND BUILD OF CARRASCAL WATER SUPPLY SYSTEM IMPROVEMENT PROJECT (PHASE II)

Activities:
*Restoration of Demolished Road Accessways and Road Pavement @ Brgy. Panikian
*Site Preparation for Hydrotesting of 10" dia. PE Pipes @ Brgy. Panikian
*Hydrotesting of 372ln.m. 10" dia. PE Pipes @ Brgy. Panikian

24/11/2023
Photos from Philkonstrak Development Corporation's post 21/11/2023

Mactan Rock Pipe Laying Lapu-Lapu City

Activities:
-Pavement Cutting
-Pavement Breaking
-Subgrade Preparation
-hauling of Excavation Materials
-hauling of sand for sand Bedding
-90 ln.m. Pipe Jointing 400 mm PE100-SDR13.6
-90 ln.m. Pipe Laying
-Backfilling with Compaction
-Warning Tape Laying

Photos from Philkonstrak Development Corporation's post 20/11/2023

Design and Build of Site Development-PSHS CVisC

Activities:

Road 1
-Concrete works on road curb and gutter
-Excavation and laying of gravel bedding for additive concrete road and curb and gutter

Entrance Symbol
-Demolition/chipping of concrete platform
-Welding works and installation of anchorage bars
-Welding works and installation of steel base plate for flame panels

Grouted riprap
-Excavation for stairs
-Installation of formworks for stairs
-Laying of riverstones for grouted riprap adjacent to stairs

Road 2 (Admin to Gym)
-Installation of rebars and formworks for road drainage
-Concrete pouring for road drainage

Covered Walk
-Installation of formworks for RC columns
-Concrete pouring for RC columns

Slope Protection
-Application of geotextile
-Installation and bending of rebars
-Concrete pouring of 1st 1.2m vertical strip from Col. 9-18

Photos from Philkonstrak Development Corporation's post 16/11/2023

Proposed 350mm dia and 100mm dia DI, Transmission and Distribution Pipeline Project

Activities:
• Breaking & Excavation of Pavement
• Pipe Laying 350mm DI Pipe - 5lengths
• Hauling of Sand & Excavated Materials
• Hauling & Lifting of power tools & barricades
• Backfill & Compaction
• Laying of Warning Tape
• Sand Bedding
• Hauling of DI Pipe to Mactan
• Cutting of Concrete Pavement

Photos from Philkonstrak Development Corporation's post 16/11/2023

Pier Enhancement and Development Project: Port Expansion with Roro Ramp

Activities:
-Backfilling
-Installation of formworks for pile cap and fender reinforcement
-Installation of precast slabs and beams
-Concrete Pouring of pile cap and fender reinforcement
-Squareholing

Photos from Philkonstrak Development Corporation's post 07/11/2023

Mactan Rock Pipe Laying Lapu-Lapu City

Activities:
• 75 ln.m. Pavement Cutting
• 18 cu.m Pavement Breaking
• 12.42sq.m. Subgrade Preparation
• 115 cu.m Excavation
• Hauling of Excavation Materials
• 24 cu.m. Sand Bedding
• 18 ln.m. Pipe Jointing 400 mm PE100-SDR13.6
• 18 ln.m. Pipe Laying
• 9.45 cu.m. Backfilling with Compaction
• Warning Tape Laying

Photos from Philkonstrak Development Corporation's post 07/11/2023

Proposed 350mm dia and 100mm dia DI, Transmission and Distribution Pipeline Project

Activities:
• Cutting of Existing Concrete Pavement @ Soong, Mactan Road
• Pipe Detect for existing pipes with MCWD Team

Want your business to be the top-listed Finance Company in Cebu City?
Click here to claim your Sponsored Listing.

Our Story

Philkonstrak Development Corporation (PDC) is a private construction firm registered in the Securities Exchange Commission (SEC) on August 2006 with SEC Registration No: CS200629243.
The professional staff at PDC has over 30 combined years of design, engineering and construction experience.

Vision:

PDC envisions being the most developed, progressive and leading construction firm globally with the highest construction category, attaining the best quality of workmanship having stable human, physical and financial resources.

CONSTRUCTION SERVICES

We specialize in design/build construction, providing single-source responsibility for the entire construction process. Our management team handles every phase and variable of the project - from architectural and engineering services thru construction administration. In the process, we will manage site selection, soil testing, environmental analysis, tax abatements and obtain the required governmental approvals and permits. We believe this process offers our clients substantial savings in time and money, without compromise design/build firm, a construction management team or a general contractor – PDC has the capabilities to serve your building needs. We also excel in the area of construction management. This variant to the traditional construction approach permits an owner to be a more interactive participant in the construction process without sacrificing time, quality or value. Whether your objective is to utilize the services of an experienced

Videos (show all)

Pier Enhancement and Development Project: Port Expansion with Roro RampActivities:- Pile Driving
Pier Enhancement & Development Project: Port Expansion with Roro Ramp
Basketball ChampionshipBBDI vs PDC
Male Volleyball ChampionshipPDC vs BBDI
Badminton Male double championshipMGR vs BBDI

Telephone

Address


Dr. 2, MGR Building Apitong Street , Sunrise Village Extension, Pardo Cebu City
Cebu City
6000

Opening Hours

Monday 9am - 5pm
Tuesday 9am - 5pm
Wednesday 9am - 5pm
Thursday 9am - 5pm
Friday 9am - 5pm
Saturday 9am - 12pm

Other Cebu City finance companies (show all)
SIMPLY TRADING SIMPLY TRADING
51 Bonifacio Street
Cebu City, 6000

Simply Trading has been at the forefront of providing first hand information about the wonderful health and skin whitening benefits of glutathione on the internet with half a deca...

CEBU HOUSING LOAN INVESTMENT PROGRAM CEBU HOUSING LOAN INVESTMENT PROGRAM
Cebu City, 6000

Welcome to Cebu Housing Loan Investment Program the Page where you can find a source of information,

Lot For Sale Lot For Sale
Cebu City, 6000

Lot for sale:For Inquiries Contact: 0917-1223983 / 0933-0137028

Cheap & Affordable lots in Cebu Philippines Cheap & Affordable lots in Cebu Philippines
Dumlog Talisay City
Cebu City, 6045

Cheap and affordable lot in Cebu, For Site Viewing Please Contact us: 09428088498 09051353148 09174448375

St. Peter SA2 Dan Imperial St. Peter SA2 Dan Imperial
Pasil
Cebu City, 6000

YOU ONLY DIE ONCE

Sun Life Financial Advisor - Erikka Denisse E. Potot Sun Life Financial Advisor - Erikka Denisse E. Potot
G/F, The Globe Tower, Panay Road Corner Samar Loop Cebu Business Park, Cebu City, Cebu
Cebu City, 6000

Prosperous Family Life Prosperous Family Life
Ceres Comp. , Tagunol Street
Cebu City, 6000

Financial Education which aims to help people be financial literate.

Nishiell Franchette Noya, Pru Life UK Licensed Financial Advisor Nishiell Franchette Noya, Pru Life UK Licensed Financial Advisor
Cebu City, 6000

Provides financial planning and support to clients in order to help clients achieve their financial

ACTFinancials - Almira Caryl Tangpos ACTFinancials - Almira Caryl Tangpos
Cebu City

ACT Towards your Financial Future

The Right Mutual Fund The Right Mutual Fund
Cebu City, 6000

Our Mission is To help create wealth for families To make a difference for families so there will be No family left behind.

PRU LIFE U.K. Financial Advisor -Maria Teresa Sarigumba PRU LIFE U.K. Financial Advisor -Maria Teresa Sarigumba
Cebu City, 6000

Licensed Life Insurance Agent at PRU-Life UK/Financial Advisor

Mutual Funds to Pinoy Growth Mutual Funds to Pinoy Growth
Cebu City, 6000

Mutual Fund and Stock Market Talks